Our pools are getting some exciting improvements beginning in January. We can’t wait for our members to experience fresher, crisper air and cleaner water at the Y!  To complete this large project, our Natatorium (pool area) will need to be closed for the month of January. We apologize for this inconvenience, but are excited for our members and the community to have an amazing new pool experience, once completed! Keep an eye on this page for updates as this project progresses!

As a Dow Bay Area Family YMCA member, you have access to other YMCA’s across the country, including nearby Saginaw Family YMCA. Click the Y logo below to see their hours of operation, pool schedule, and more!

PROGRESS MADE

As soon as the New Year was here, our staff and contractors were hard at work to begin this project. Here is a list of the progress we’ve made on this project so far!

  • Slide has been re-caulked on the inside
  • Tile work has been done on both pools and columns
  • Contractors have started removing and replacing sand in the filter system
  • The old UV system has been removed
  • Plumbing and electrical work is currently 75% complete
  • Pool Pak unit  has been prepped for removal
  • Contractors have started removing current duct work (you may have noticed the giant lifts in our South Parking Lot!)
  • New air unit has arrived and is in place
  • Old Pool Pak unit has been taken off the roof
  • Electrical and plumbing work will be completed
  • New air quality unit has been placed in its permanent home in the South parking lot
  • All old ducting in the natatorium  has been removed

UPDATED 1.19.22

  • Pool filters changed with upgraded media.
  • Ventilation and dehumidification unit removed and replaced with new EASi unit and vent sock!
  • All pools grouted.
  • Tile work underway.